Worker burned following contact with power line

August 4, 2021

A vertical farming, glasshouses and energy company has been sentenced after a worker came into contact with an 11kV overhead power line.

On 3 December 2018, a subcontractor scaffolding worker was unloading some scaffolding poles near power cables in Willerby, Hull, when one of the poles caught the overhead line. He sustained burns to his leg and foot and was hospitalised.

The HSE’s investigation found that the site was very muddy, and operatives were unable to park their vehicles on site near the work area, meaning they had to move the materials onto the site by hand. There were also inadequate controls on site to warn of the overhead cables.

Cambridge Glasshouse Company Limited of Wallingfen Park, Main Road, Newport Brough, East Yorkshire pleaded guilty to breaching Section 14 of the Electricity at Work Act 1989. The company was fined £333,333 and ordered to pay costs of £1,235.

Speaking after the hearing, HSE inspector Sarah Robinson said: “The company should have planned the work to mitigate the risks and had better signage and controls around the site for overhead cables.

“This was a very serious incident and could have easily been fatal.”

 

This is valid as of 4th August 2021.

A vertical farming, glasshouses and energy company has been sentenced after a worker came into contact with an 11kV overhead power line. On 3 December 2018, a subcontractor scaffolding worker was unloading some scaffolding poles near power cables in Willerby, Hull, when one of the poles caught the overhead line. He sustained burns to his leg and foot and was hospitalised. The HSE’s investigation found that the site was very muddy, and operatives were unable to park their vehicles on site near the work area, meaning they had to move the materials onto the site by hand. There were also inadequate controls on site to warn of the overhead cables. Cambridge Glasshouse Company Limited of Wallingfen Park, Main Road, Newport Brough, East Yorkshire pleaded guilty to breaching Section 14 of the Electricity at Work Act 1989. The company was fined £333,333 and ordered to pay costs of £1,235. Speaking after the hearing, HSE inspector Sarah Robinson said: “The company should have planned the work to mitigate the risks and had better signage and controls around the site for overhead cables. “This was a very serious incident and could have easily been fatal.”   This is valid as of 4th August 2021.
[ssba-buttons]

You May Also Be Interested In

Comments are closed.

✉ Sign up to the Barbour Newsletter

Free downloads, advance notice of webinars, product updates and perks – all straight to your inbox.

  • Barbour EHS may from time to time send updates about Barbour products and services. By providing your contact information you consent to being contacted for direct marketing purposes by Barbour EHS. Please ensure you review our Privacy Policy.